Wednesday, November 14, 2012

Mishawaka - Penn Public Library

The Mishawaka-Penn Public Library commissioned Lehman & Lehman to determine the most cost effective solution to restoring their embankment, while preventing future erosion and providing a visual impact. The solution was to remove the existing vegetation and construct a modular block retaining wall to lessen the slope. Flowering shrubs and perennials were then installed to stabilize the bank. Fuerbringer Landscaping & Design was the contractor for the project. The photos below show the construction process.
6.5.13 Embankment Landscape Restoration in bloom
6.5.13 Embankment Landscape Restoration in bloom
6.5.13 Embankment Landscape Restoration in bloom
11.7.12 Project completed late fall
11.7.12 Project completed late fall
10.23.12 Bank stabilized by heavy-duty erosion control fabric - plants installed through fabric
10.23.12 Wall construction complete - landscaping installed
10.23.12 Wall construction complete - landscaping installed
10.10.12 East wall nearing completion
10.10.12 Construction of south wall - installation of 2nd layer of geo-grid reinforcement
10.10.12 Construction of south wall - installation of 2nd layer of geo-grid reinforcement
10.3.12 Construction of east wall - view from top of bank
10.3.12 Stacking block on geo-grid - continuing to increase wall height
10.3.12 Installation of first of two geo-grid reinforcement layers
10.2.12 New wall construction - view from top of bank
10.2.12 New wall construction - view from top of bank
10.2.12 Stacking & leveling block courses
10.2.12 Construction of wall base
10.1.12 Cleared east embankment; excavation for new wall
10.1.12 Cleared south embankment
10.1.12 Base preparation for new wall
9.27.12 Existing south embankment with 1:1 slope
9.27.12 Existing east embankment with 2:1 slope
9.27.12 Existing embankment transition area from 2:1 to 1:1 slope
9.27.12 Existing fence being removed for access

No comments: