The trailhead layout and design will be located east of State Road 13. It will include the development of a rest area equipped with picnic tables, benches, a drinking fountain and bike racks. In addition, the trailhead design will include an information kiosk about the Pumpkinvine Trail. Located off the west side of County Road 43, the new parking lot will serve users of the trail. It will accommodate ten vehicles and will have two spaces that are handicap accessible with easy access to the adjacent trail.
Bridge rehabilitation work will occur on three former railroad bridges. One spans the south fork of Pine Creek and the other two span Mather Ditch and East Lake Ditch. The bridge work will include bank stabilization and stream realignment as well as the replacement of existing piles, ties, back walls, and new decking, rail systems and concrete approaches.
Construction by bridge contractor, Beer & Slabaugh, is in progress. Bridge completion is scheduled for June. The completion of the trailhead is set for September, 2009 and the parking lot in 2010. Photos showing "Before", "In-Progress" and "Final" stages of construction for each of the three bridges, parking lot and trailhead are below.
SOUTH PINE CREEK BRIDGE "FINAL"
6.2.09 Approaching the renovated bridge from the east - Final segment of trail ready to be paved
6.2.09 Completed bridge renovation - New bridge decking, railing and concrete approaches
6.2.09 Old supports New - Decades old substructure supports new Pumpkinvine Pedestrian Trail
6.2.09 Newly contoured embankment stabilized with erosion control fabric and native seeding
6.2.09 View of new bridge looking towards County Road 33 and the cleaned up former railroad corridor
SOUTH PINE CREEK BRIDGE "IN-PROGRESS"
5.19.09 Re-aligned South Pine Creek with glacial stone bank stabilization
5.19.09 View looking east across the renovated bridge from the west bridge approach
5.19.09 View looking west where the new approach and guardrail meet the existing trail
5.19.09 Subgrade and base preparation for the east approach
5.19.09 New bridge railing cantilevered supports tied into the existing substructure
5.19.09 New bridge railing
5.19.09 New bridge deck surface abutting the concrete approach
5.19.09 Glacial stone bank stabilization
5.19.09 South Pine Creek Bridge renovation nearing completion
SOUTH PINE CREEK BRIDGE "IN-PROGRESS"
SOUTH PINE CREEK BRIDGE "BEFORE"
10.3.08 View looking east across the existing bridge and along the existing trail corridor toward County Road 33
7.2.08 Existing South Pine Creek Bridge
7.2.08 Existing temporary decking and deteriorating cross ties
7.2.08 View upstream (north) under existing bridge
7.2.08 Current stream location and center pile bent
7.2.08 Existing west abutment and severe bank erosion
PARKING LOT "BEFORE"
PARKING LOT "BEFORE"
TRAILHEAD "BEFORE"
(north side of proposed trail)
MATHER DITCH BRIDGE "IN-PROGRESS"
MATHER DITCH BRIDGE "BEFORE"
Mather Ditch Bridge
Pumpkinvine Trail Corridor
EAST LAKE BRIDGE "IN-PROGRESS"
EAST LAKE BRIDGE "BEFORE"