The project consists of two trail segments. The first is the Cumberland Crossing Loop that follows Vale Park Road west to Valparaiso Street, north on Valparaiso Street to Bullseye Lake Road, then east on Bullseye Lake Road to the new Cumberland Road extension. This segment is an 8-foot wide asphalt trail in an open right-of-way and is approximately 1 mile in length.
Segment two is a concrete sidewalk that begins at Valparaiso High School and continues south to Ogden Gardens Park. The new 8-foot wide concrete pathway is replacing an old 4-foot wide walk and is approximately 1 mile in length as well. This segment is in a narrow right-of-way and crosses numerous commercial and residential properties. Some right-of-way acquisition was necessary.
Construction began in August 2007, with completion set for May 2008. Below, you will find project photos, with the most recent photos first.
....................................................................................................
....................................................................................................
Campbell Street
3.31.08 Existing open drain prior to reshaping and
bridge construction
3.31.08 Heavy rains leave water at new bridge location
3.31.08 Fresh concrete along the final sections of the pathway
3.31.08 Fresh concrete along the final sections of the pathway
3.31.08 Final base preparation for the remaining
sections of the pathway
....................................................................................................
3.17.08 Excavation and base installation complete –
existing residential retaining wall protected
3.17.08 Construction crews prepare to excavate
for a new concrete retaining wall and stairs
3.17.08 Demolition of existing stairs and
sidewalk along pathway route
....................................................................................................
12.12.07 New concrete apron for property owners
adjacent to trail
12.12.07 New ADA Compliant curb ramps
12.12.07 Accommodation of existing utility infrastructure
12.12.07 New 8’ pathway in front of Valparaiso High School
.....................................................................................................
11.28.07 Demolition complete – pathway route ready
for new curb ramps and sidewalk
11.28.07 Demolition and excavation continues along Campbell St.
.....................................................................................................
Campbell Street
3.31.08 Existing open drain prior to reshaping and
bridge construction
3.31.08 Heavy rains leave water at new bridge location
3.31.08 Fresh concrete along the final sections of the pathway
3.31.08 Fresh concrete along the final sections of the pathway
3.31.08 Final base preparation for the remaining
sections of the pathway
....................................................................................................
3.17.08 Excavation and base installation complete –
existing residential retaining wall protected
3.17.08 Construction crews prepare to excavate
for a new concrete retaining wall and stairs
3.17.08 Demolition of existing stairs and
sidewalk along pathway route
....................................................................................................
12.12.07 New concrete apron for property owners
adjacent to trail
12.12.07 New ADA Compliant curb ramps
12.12.07 Accommodation of existing utility infrastructure
12.12.07 New 8’ pathway in front of Valparaiso High School
.....................................................................................................
11.28.07 Demolition complete – pathway route ready
for new curb ramps and sidewalk
11.28.07 Demolition and excavation continues along Campbell St.
.....................................................................................................
.....................................................................................................
Cumberland Loop
11.16.07 Final trail paving through existing woods
11.16.07 Final trail paving through existing woods
11.16.07 Constructed trail along Valparaiso Street
11.16.07 Trail terminated at new pedestrian bridge location
......................................................................................................
11.5.07 Trail excavation and aggregate base installation –
Vale Park Road East
11.5.07 Trail excavation and aggregate base installation –
Vale Park Road West
11.5.07 Trail excavation at Vale Park Road and
Valparaiso Street intersection
11.5.07 Trail sub base compaction
11.5.07 Excavated and compacted subgrade
for trail along Valparaiso Street
11.5.07 Site clearing at bridge location
......................................................................................................
Campbell Street Existing Conditions
10.1.07 Proposed concrete pathway/
sidewalk improvements – ADA ramp
10.1.07 Proposed concrete pathway/
sidewalk in front of Valparaiso High School
10.1.07 Proposed commercial drive concrete apron improvement
10.1.07 Proposed pathway improvements and landscape renovation
10.1.07 Proposed pathway and private residential stair improvement
10.1.07 Proposed pathway improvement – utility accommodation
10.1.07 Proposed residential drive concrete apron improvements
......................................................................................................
Cumberland Loop Existing Conditions
8.28.07 Proposed asphalt trail path location
along Vale Park Road (view to east)
8.28.07 Proposed asphalt trail path location
along Vale Park Road (view to west)
8.28.07 Proposed pedestrian bridge location
8.28.07 Proposed asphalt trail path
location along Valparaiso Street
1 comment:
Sorry it took me so long to find this great site. I live in Valpo and love what Jon Costas and the parks department are doing to improve our quality of living
Post a Comment